Education Client: Lancaster, Pennsylvania

Location: Lancaster, PA

Length: 2 Weeks

Estimated Completion Date: 8/6/20

Scope: The DWM Construction & Renovation team began bidding out this tenant improvement job in January. DWM was awarded the contract to complete this 1-1.5 week project for a national retail/education client. This is Phase 1 of 2 Phases; Phase 1 scope consists of ( trades, General & Flooring, as well as on-site project management by 2 DWM Construction & Renovation Project Managers.

General Scope:

Phase 1:

  • Disassemble existing wall fixtures prior to flooring demo to allow for new floor coverings to be installed up to demising walls

  • Relocate & stage existing floor fixtures prior to flooring demo

  • Demo of all associated floor coverings on 2nd floor of Bookstore

  • Prep sub-floor as required prior to installation of new floor

  • Install (2) variants of luxury vinyl plank floor covering, associated transition strips

  • Re-set all existing floor fixtures

  • Re-install dissembled wall fixtures

  • Dispose of all discarded work debris in dumpster

  • Provide a general cleanup of all work spaces prior to handing space back over to store personnel

Phase 2:

  • Provide necessary equipment (dollies, hand trucks, flat bed cart, etc.) and manpower to receive deliveries of wood & metal materials

  • Dispose of unwanted fixtures & debris in dumpster

  • Supply & install any necessary strapping for wall fixtures

  • Install provided wall fixtures in their designated locations

  • Relocate floor fixtures to their new designated location as per plan

  • Patch & prep any existing blemishes in walls

  • Supply & install (2) coats paint on all walls throughout

  • Sand and prep (2) sets of wood stairs receiving new stain

  • Supply & apply stain over (2) sets of stairs

  • Supply and install track lighting as per plan

  • Disconnect existing valance lighting for (2) 3' wall fixtures. Save lighting for reuse.

  • Re-install valance lighting once wall fixtures are relocated.

  • Install provided track lighting as per plan.

  • Supply and install (1) vestibule pendant light fixture

  • Dispose of all discarded work debris in dumpster

  • Provide a general cleanup of all work spaces prior to handing space back over to store personnel