Retail Client: Raynham, MA

Location: Raynham, MA

Length: 4 Weeks

Estimated Completion Date: 10/4/19

Scope: The DWM Construction & Renovation team began bidding out this white box job in ​May. DWM was awarded the contract to complete this 30 day project for a national retail real estate client. The full project scope has 7 different trades, including GC, plumbing, electrical, HVAC, flooring, painting, and roofing . This white box project will take a vacant 5,700 Sq. Ft of unfashionable retail space and turn it into a functional blank slate for future tenants use. This project includes on-site project management by a DWM Construction & Renovation project manager.

Scope of Work:

  • Removing 5,700 Sq. Ft of flooring (rolled carpet and VCT)

  • Demolition of framed wall impeding on visibility through window glazing

  • Demolition of existing ceiling suspended strip lighting Removal of all related demolition debris off site.

  • Construct two ADA compliant restrooms

    • Rough-in waste line and new 3" vent penetration through the roof

    • Bring water supply 180' from the main building supply to provide service for two new bathrooms

    • Frame, hand gypsum board, paint, and VCT floor

    • Accessory install (ADA compliant grab bars, beveled edge mirror, paper towel dispenser, waste paper cabinet, signage needed by building code)

    • Install motion sensor switch and lighting for both restrooms

    • Bathroom fan ventilation

  • Install 5,700 Sq. Ft of drop ceiling grid and tiles approximate 10' AFF

  • Insulate, hang gypsum board, tape, and prep for paint 120' demising wall.

  • Relocate approximately 55 fire sprinkler heads to be flex adjust into new drop ceiling

  • Install approximate 55 2x4 drop in lights in new drop ceiling Install duplex receptacles along demising wall per code

  • Test and update emergency lighting throughout the space to local code

  • Supply and install of 10 gal. water heater, bubbler, and utility sink

  • Removal and discard of two existing RTU's

    • Disconnect electrical and gas to existing 6 ton and 10 ton RTU's

  • Furnish and Install two Roof Top Air Handling Units

    • Rigging and dropping new 7 ton and 10 ton roof top units onto roof

    • Adjusting curb adapters

    • install two economizers

    • RGD's for new 10' drop ceiling and two bathrooms

    • Rework duct work as needed

    • Supply and insulate duct work per code

    • Run two thermostat wires for new RTU's

    • Test all equipment

  • Supply and install two 3'x7' wood doors with knock down metal frames with privacy locks.

  • Paint and install FRP in both bathrooms.